Progress continues, and we have now used the first reel of conduit. 2500'+ now in the ground and we about 50% through the first trunk line.
In the evenings we are also continuing the development of the test lab, and doing lots of spicing of the fiber to ensure we ready to go when we begin the home installs in the next couple weeks.
The current plan is to get Trunk A in the ground, and the handholes in place. Once that is done, we can pull the main 144 strand fiber through, and then begin splicing at the splice points to deliver service to the homes.
Our plan still remains to have at least the first 10 homes lit by the end of June. The current pace means we should be able to exceed that.